用列表法设计箭线图的基本规则

宁宣熙   

  1. 南京航空学院
  • 收稿日期:1987-11-22 修回日期:1900-01-01 出版日期:1989-02-25 发布日期:1989-02-25

THE FUNDAMENTAL RULES OF CONSTRUCTING A ARROW DIAGRAM WITH THE TABULATION ANSWER METHOD

Ning Xuanxi   

  1. Nanjing Aeronautical Institute
  • Received:1987-11-22 Revised:1900-01-01 Online:1989-02-25 Published:1989-02-25

摘要:

在“计划网络图的计算机辅助设计和绘制方法”一文中,介绍了用列表法设计箭线图的基本原理。本文将详细介绍它的基本规则。 1.专用名词定义 为了叙述方便,将构成一项工程的各项作业称为目标作业,它们各自的先行作业称为目标作业的先行作业集合。

关键词: 计划评审技术, 关键路线法, 计算机辅助设计

Abstract:

In PERT anb CPM the first arrow diagram has long been drawn by hand according to the given logical relationships. It is tirne-eonsuming and troublesome.In order to implement computer-aided construction of an arrow diagram a new method called "Tabulation Answer Method" was developed .This paper introduces the fundamental rules of this new method.

Key words: program evaluation and review technique, critical path method, computer aided design