电子电器工程与控制

装备研制项目的模糊挣值管理方法

  • 吴诗辉 ,
  • 解江 ,
  • 刘晓东 ,
  • 贺波 ,
  • 闫宝会 ,
  • 郭亚坤
展开
  • 1. 空军工程大学 装备管理与安全工程学院, 西安 710051;
    2. 解放军93705部队修理厂, 遵化 064200;
    3. 解放军95876部队, 山丹 734100

收稿日期: 2016-03-24

  修回日期: 2016-10-08

  网络出版日期: 2016-10-14

基金资助

国家自然科学基金(61601501);陕西省自然科学基金(2014JM2-6095)

Method of fuzzy earned value management for weapon equipment development project

  • WU Shihui ,
  • XIE Jiang ,
  • LIU Xiaodong ,
  • HE Bo ,
  • YAN Baohui ,
  • GUO Yakun
Expand
  • 1. Equipment Management and Safety Engineering College, Air Force Engineering University, Xi'an 710051, China;
    2. Repair Factory, No. 93705 Unit of PLA, Zunhua 064200, China;
    3. No. 95876 Unit of PLA, Shandan 734100, China

Received date: 2016-03-24

  Revised date: 2016-10-08

  Online published: 2016-10-14

Supported by

National Natural Science Foundation of China (61601501); Natural Science Foundation of Shaanxi Province (2014JM2-6095)

摘要

由于装备研制项目广泛存在着技术风险,其预算成本难以用确定数描述,而现有挣值管理技术通常用确定数描述项目费用基线,忽视了项目的技术风险因素。为此,将技术风险引入挣值管理(EVM)方法,提出了一种装备研制项目的模糊挣值管理(FEVM)改进方法。该方法充分考虑了装备研制中的技术风险问题,利用技术成熟度(TRL)对项目计划成本进行估算,在此基础上,利用模糊数学理论,给出了一种基于可能度的高风险项目的成本和进度的模糊评价标准,并对项目的完工成本(ECC)和完工时间(ECT)进行了模糊预测。最后,通过案例对文中的方法进行了阐述。该方法针对装备研制项目技术风险大的特点,进一步拓展了挣值管理的适用性,对于决策者控制风险、保证项目的费用和进度具有一定指导意义和参考价值。

本文引用格式

吴诗辉 , 解江 , 刘晓东 , 贺波 , 闫宝会 , 郭亚坤 . 装备研制项目的模糊挣值管理方法[J]. 航空学报, 2017 , 38(2) : 320258 -320272 . DOI: 10.7527/S1000-6893.2016.0266

Abstract

Since technology risk exists widely in the weapon equipment development project, it is better to describe the budget as fuzzy number. However, technology risk is neglected in the current earned value management (EVM), which often builds the baseline of the budget with crisp numbers. Therefore, we introduce technology risk to EVM, and propose an improved method of fuzzy earned value management (FEVM) for the weapon development project. The proposed FEVM fully considers technology risk during the project development, and applies the technology readiness level (TRL) concept to estimate the budgeted cost. By utilizing fuzzy theory, the fuzzy assessment standard based on degree of possibility for the cost and schedule of high risk project is given, as well as fuzzy prediction of the estimate completion cost (ECC) and estimate completion time (ECT). The proposed method is illustrated through an example. The proposed method extends the applicability of the EV techniques for the weapon equipment development project with technology risks, and can better help decision-makers to control risks and bring cost and schedule back to the baseline.

参考文献

[1] KEVIN T C. A comparison of earned value management and earned schedule as schedule predictors on DoD ACAT I programs[D]. Ohio:Air Force Institute of Technology, 2013.
[2] SIDNEY W H. An investigation of possible discriminating earned value variables in department of defense major acquisition program cancellation[D]. Monterey:Naval Postgraduate School, 2013.
[3] DELGADO H N, RHODESIDE G R. Results of a NASA kennedy space center earned value management pilot project[R]. Washington, D.C.:Kennedy Space Center, 2004.
[4] NAENI L M, SHADROKH S, SALEHIPOUR A. A fuzzy approach for the earned value management[J]. International Journal of Project Management, 2011, 29:764-772.
[5] NAENI L M, SHADROKH S, SALEHIPOUR A. Evaluating fuzzy earned value indices and estimates by applying alpha cuts[J]. Expert Systems with Applications, 2011, 38(7):8193-8198.
[6] 戴育雷, 李南, 杨莉. 基于模糊理论的挣值管理方法[J]. 计算机仿真, 2013, 30(3):213-216. DAI Y L, LI N, YANG L. Method of earned value management method based on fuzzy theory[J]. Computer Simulation, 2013, 30(3):213-216(in Chinese).
[7] PONZ-TIENDA J L, PELLICER E, YEPES V. Complete fuzzy scheduling and fuzzy earned value management in construction projects[J]. Journal of Zhejiang University-SCIENCE A (Applied Physics & Engineering), 2012, 13(1):56-68.
[8] MORTEZA B, ABALFAZL, SIAMAK N, et al. Designing a control mechanism using earned value analysis:An application to production environment[J]. The International Journal of Advanced Manufacturing Technology, 2010, 49:419-429.
[9] CHENG C H. Evaluating weapon systems using ranking fuzzy numbers[J]. Fuzzy Sets and Systems, 1999, 107:25-35.
[10] ZIMMERMANN H J. Fuzzy set theory and its application[M]. London:Kluwer Academic Publishers, 1996.
[11] 吴坚. 一种新的梯形模糊数互补判断矩阵的排序方法[J]. 中国管理科学, 2010, 18(3):95-100. WU J. A new approach for priorities trapezoidal fuzzy number reciprocal judgement matrix[J]. Chinese Journal of Management Science, 2010, 18(3):95-100(in Chinese).
[12] KAUFMAN A, GUPTA M M. Introduction to fuzzy arithmetic:Theory and application[M]. New York:Van Nostrand Reinhold, 1985.
[13] CHANG D Y. Applications of the extent analysis method on fuzzy AHP[J]. European Journal of Operational Research, 1996, 95:649-655.
[14] 李保平. 装甲装备研制项目风险评价及管理研究[D]. 长沙:国防科学技术大学, 2010. LI B P. Study on risk assessment and management of development project for armored equipment[D]. Changsha:National University of Defense Technology, 2010(in Chinese).
[15] 冷静, 齐欢, 董鹏. 大型舰船平台购置费影响因素及其预测技术方法研究[J]. 舰船科学技术, 2010, 32(2):77-82. LENG J, QI H, DONG P. Study on influence factors and forecast technology of large warship's platform purchase value[J]. Ship Science and Technology, 2010, 32(2):77-82(in Chinese).
[16] MALONE P, SMOKER R, APGAR H, et al. The application of TRL metrics to existing cost prediction models[C]//IEEE Aerospace Conference. Piscataway, NJ:IEEE Press, 2011:1-12.
[17] CHANG L S. Software documents quality measurement-a fuzzy approach[C]//IEEE International Conference on Information Theory and Information Security (ICITIS). Piscataway, NJ:IEEE Press, 2010:88-92.
[18] Project Management Institute. Project management body of knowledge (PMBOK)[M]. 2nd ed. Newtown Square:Project Management Institute, 2000.
[19] 中华人民共和国国家质量监督检验检疫总局,中国国家标准化管理委员会. 科学技术研究项目评价通则GB/T22900-2009[S]. 北京:中国标准出版社, 2009. AQSIQ, SAC. General rules for the science and technology project evaluation:GB/T22900-2009[S]. Beijing:Chinese Standard Press, 2009(in Chinese).
[20] 李思. 基于TRL武器装备研制项目定价模型研究[D]. 长沙:国防科学技术大学, 2011. LI S. Analysis on TRL-based in field of weapon system price[D]. Changsha:National University of Defense Technology, 2011(in Chinese).
[21] Project Management Institute. Practice standard for earned value management[M]. Newtown Square:Project Management Institute, 2005.
[22] 熊琴琴, 毛晔. 国外项目挣值管理研究述评[J]. 科技管理研究, 2013(19):166-169. XIONG Q Q, MAO Y. Review on the external study of project earned value management[J]. Science and Technology Management Research, 2013(19):166-169(in Chinese).
[23] 薛定宇,陈阳泉. 高等应用数学问题的MATLAB求解[M]. 第3版. 北京:清华大学出版社, 2013. XUE D Y, CHEN Y Q. Advanced applied mathematical problem solutions with Matlab[M]. 3rd ed. Beijing:Tsinghua University Press, 2013(in Chinese).

文章导航

/